Quaker Lane

SPS Compound complete. Rising main complete to the tie in MH through the highway. Access road 90% complete, only remaining works are the section at the entrance gate and the area at the SPS compound which cannot be completed
until the PS is live and the old septic tanks which are in the road line can be demolished. The BT line is installed but is not live and this will delay completion. Additional works being discussed includes a new gate at the field entrance and stock-proof fencing along the access road.